42.   Company's liability for failure to supply electricity

Where a certificate approving the supply of electricity is issued in accordance with the regulations made under this Act to an intended consumer and such consumer pays to the Company not later than one month before the date of the expiry of the certificate such deposit or contribution as may be required by the Company and the Company fails, within one month from the date of payment, to supply electricity to such consumer and does not give to the Chief Electrical Engineer a satisfactory explanation for its failure so to do, the Company is liable to pay the fee in respect of a fresh certificate approving the supply of electricity.