Revised Laws of Saint Lucia (2021)

31.   Effect of non-submission of interim return

Where —

  1.  

    (a)     the interim return is not submitted to the Commission within the time specified in section 30(1); or (Amended by Act 2 of 2016)

  1.  

    (b)     the Company, before the interim return is submitted demands payment for electricity supplied for any purpose in the then current financial year; and

  1.  

    (c)     the Company charges for electricity supplied at the basic energy rates in force at the end of the financial year immediately preceding the then financial year;

     then any decrease under section 30(3) or increase under section 30(4) is effective from the beginning of the then current financial year; but any such decrease or increase must be distributed and allocated equally on a monthly basis over the remaining months in the then current financial year.